The diagram shows the activity network for a project, with the times of the activities in days and an empty scanning box at each event. Activity takes day and activity takes day. Find the float time of activity , in days.
Worked solution
Forward pass: the earliest time at event 4 is the larger of and , which is days.
The earliest time at event 5 is the larger of and , so the minimum completion time is days.
Float of days.
Answer
Marking guidelines
Carries out the forward pass to find the earliest time at the event where C and D meet | 1 mark |
Finds the earliest time at the final event, which is the minimum completion time | 1 mark |
Subtracts the earliest start and the duration of F from the latest finish to find the float | 1 mark |
Report a problem with this question.
